Project Details
Title: Weyand Canal Automation Project
Summary: Under the Proposed Action, Reclamation would provide grant funding for the District to demolish and reconstruct four existing reinforced concrete check structures with modifications such that the new control structures can be mounted, saw-cut portions of existing concrete structure, the removal of the existing weir boards and the installation of automated Rubicon Flume Gates. In addition, the District will modify 10 turnout and lateral structures, one spill structure, and integrate two pumped services. All Project-related activities will occur within the District's ROW when the canal is dewatered during the non-irrigation season. The purpose of the Project is to install automated control structures to more efficiently distribute irrigation water to adjacent agricultural lands.
Contact
Phone
Fax
E-Mail
Notes
Sarah Perrin 916-537-7063 N/A sperrin@usbr.gov
Status
11/01/2018FONSI Signed
List of Available Reports
File Report Title File Ext File Size
Environmental Assessment, Weyand Canal Automation Project .pdf 5,377,384 B
FONSI, Weyland Canal Automation Project .pdf 305,155 B