Anderson Ranch Dam Raise
Milestones
Summer 2022 | Complete dam spillway overlay feasibility design |
Spring 2023 | Complete dam raise 30% design and cost estimate |
Winter 2023/2024 | Complete environmental compliance |
Summer 2024 | Complete final design |
November 2021 | IWRB and Reclamation signed and executed cost-share contract. IWRB provided first interval payment of advanced funds. TSC initiated final design activities. |
Sept. / Oct. 2021 | Reclamation and IWRB completed cost-share contract negotiation sessions: Sept. 22, Oct. 5, Oct. 19, and Oct. 28. |
July / August 2021 | Reclamation’s Columbia-Pacific Northwest Region requested delegation of authority and received approval from the Commissioner to negotiate, execute, and administer a cost-share agreement pursuant to section 4007 of the WIIN Act with the IWRB. |
May 2021 | Initiated pause in the environmental compliance process pending further development of final design. |
December 2020 | Fiscal Year 2021 appropriations legislation secured $12.88 million in WIIN Act funding for completing the study, environmental compliance, and construction. |
December 2020 | Reclamation transmitted the final Feasibility Report to Congress. |
December 2020 | The Secretary of the Interior determined the Study’s recommended plan to be feasible in accordance with the WIIN Act. |
July 31, 2020 | Reclamation released the draft environmental impact statement and draft feasibility report. |
April 6-10, 2020 | Reclamation completed the peer review of the Water Operations Technical Memorandum. |
February 3-7, 2020 | Reclamation completed the design, estimate, and construction review of the feasibility level designs. |
August 27-29, 2019 | Reclamation conducted public scoping open houses in Pine, Boise, and Mountain Home, Idaho. |
August 9, 2019 | Reclamation published the notice of intent for an environmental impact statement in the Federal Register. |
June 19, 2019 | Reclamation’s Technical Service Center completed feasibility-level design and cost estimates for the Anderson Ranch Dam raise. |
June 7, 2019 | IWRB filed a water right permit application for the potential additional storage (Water Right No. 63-34753). |
April 30, 2019 | Consultant submitted land, structure, infrastructure, and real estate impact assessment (rim analysis) for Anderson Ranch Reservoir. |
December 25, 2018 | Reclamation awarded an indefinite delivery / indefinite quality contract for architect and engineering services to Sundance-EA joint venture to complete the study and environmental compliance activities. |
December 3-7, 2018 | Reclamation conducted a value planning study and received a final accountability report in February 2019. |
November 8, 2018 | Reclamation and IWRB hosted an informational public open house in Boise, Idaho. |
August 28, 2018 | Reclamation and IWRB hosted a legislative infrastructure tour to discuss large water infrastructure projects in Idaho with representatives from Idaho’s congressional delegation. |
July 27, 2018 | IWRB passed a resolution supporting narrowing the focus of the Study to a raise at Anderson Ranch Dam. |
Nov. 2017 – Jan. 2019 | Reclamation completed initial screening of the three potential dam raise alternatives and developed a project management plan. |