Nathaniel "Nat" Washington Power Plant Overhaul Project — Project Schedule

Tentative Schedule
Activity Start Finish
Overhaul Units G22-24 March 2013 Sept. 2021
Overhaul G-24 March 2013 April 2016
Overhaul G-23 April 2016 Feb. 2019
Overhaul G-22 March 2019 Sept. 2021
Overhaul Units G19-G21 TBD TBD