Maintenance Equipment on the Scene at Scoggins Dam

Media Contact: Diana Cross , (208) 378-5020

For Release: September 18, 2003

Work on the spillway gates at Scoggins Dam has begun, according to the Bureau of Reclamation. The dam's spillway gates will be reinforced to bring them up to the agency's current seismic standards.

Scaffolding has been erected to enable crews to reinforce the spillway gate arms. Work is expected to be completed by the middle of October.

Reclamation officials stress that the dam is safe, and that the modifications are designed to meet current seismic criteria. The work is being completed based on an agency-wide evaluation of radial arm gates, similar to those at Scoggins Dam.

Scoggins Dam, located on the Tualatin River, was completed in 1978 and provides irrigation water from Henry Hagg Reservoir for approximately 17,000 acres.

# # #

The Bureau of Reclamation is a federal agency under the U.S. Department of the Interior and is the nation's largest wholesale water supplier and second largest producer of hydroelectric power. Our facilities also provide substantial flood control, recreation opportunities, and environmental benefits. Visit our website at https://www.usbr.gov and follow us on Twitter @USBR; Facebook @bureau.of.reclamation; LinkedIn @Bureau of Reclamation; Instagram @bureau_of_reclamation; and YouTube @reclamation.