News Release Archive

$1.7 Million Contract Award for Work at American Falls Reservoir

Media Contact: Annette Ross, (208) 378-5322, aross@usbr.gov
Robert Boyer, rboyer@usbr.gov

For Release: September 14, 2016

BOISE, Idaho - The Bureau of Reclamation awarded a $1.7 million construction contract Sept. 9 to Yale Creek, Inc., a small business based in Rexburg, Idaho, for an improvement project on the American Falls Reservoir. The project involves rehabilitation of the West Side boat ramp, parking area and restroom facilities, located adjacent to the dam. American Falls Dam is approximately 26 miles west of Pocatello, Idaho.

After more than 55 years of continual use and exposure to the elements, the West Side boat ramp along American Falls Reservoir has reached the end of its functional life. The ramp and parking area are showing considerable signs of deterioration and are in need of replacement.

"We are excited to see this project move forward," said Ryan Newman, Upper Snake Field Office assistant manager. "The new ramp will provide for improved, safe, reservoir access and should accommodate the public's needs."

On-site work is expected to begin the fall of 2016 with completion in March 2018.

American Falls Dam was originally completed in 1928. The dam is part of the Minidoka Project and is located on the Snake River near American Falls. In 1978, the dam was reconstructed and replaced under the authority of Reclamation's Safety of Dams Act.

# # #

The Bureau of Reclamation is a federal agency under the U.S. Department of the Interior and is the nation's largest wholesale water supplier and second largest producer of hydroelectric power. Our facilities also provide substantial flood control, recreation opportunities, and environmental benefits. Visit our website at https://www.usbr.gov and follow us on Twitter @USBR; Facebook @bureau.of.reclamation; LinkedIn @Bureau of Reclamation; Instagram @bureau_of_reclamation; and YouTube @reclamation.