Reclamation Prepares EA on Proposed John W. Keys, III Pump-Generating Plant Modernization

Media Contact: John Redding, (208) 378-5212, 07/01/2011 14:21
Lynne Brougher, lbrougher@usbr.gov

For Release: July 01, 2011

The Bureau of Reclamation is requesting public comment to help identify issues to be addressed in an Environmental Assessment (EA) for the proposed John W. Keys, III Pump-Generating Plant Modernization Project. The pump-generating plant is located at Grand Coulee Dam on the Columbia River about 90 miles west of Spokane, Washington.

Information obtained during the scoping period from July 6 - August 5, 2011, will help bring focus to the concerns, issues, and analyses that should be included in the draft EA which is scheduled to be issued by December of 2011. Completion of the final EA is anticipated in March 2012.

The John W. Keys, III Pump-Generating Plant provides irrigation water to about 670,000 acres of farmland in the Columbia Basin Project. It has a hydroelectric generating capacity of 314 megawatts and has been in operation since the early 1950s. The plant contains 6 pumps and 6 pump-generators.

The purpose of the modernization project is to replace and increase the plant's operational reliability by replacing and repairing components that are exhibiting substantial age-related wear. This proposed modernization, if approved, will be jointly funded by the Bonneville Power Administration and the Columbia Basin Project irrigation districts to ensure efficient plant operations to provide reliable irrigation delivery and hydroelectric power.

The three proposed alternatives include:

- No Action: Reclamation would continue operating the John W. Keys, III Pump-Generating Plant's pump and pump-generating units with no system improvements.

- Plant Modernization: Reclamation would overhaul and modernize the pump and pump-generating units. This would include work on the unit controls, transformers, circuit breakers, and the fire protection equipment.

- Plant Modernization with Left Powerhouse Decoupling (Disconnecting): Reclamation would overhaul and modernize the pump and pump-generating units. The pumps will be disconnected, also known as decoupling, from the Grand Coulee left powerhouse and connected to the Grand Coulee 230 kV switchyard. This would require an additional transformer and installation of a new 230 kV transmission line to connect the pumps to the switchyard.

A Draft EA is scheduled to be available for public review by December of 2011. The Project Summary can be found at www.usbr.gov/pn/programs/ea/wash/jkpgp/index.html. Written comments can be sent to Keith McGowan, Environmental Protection Specialist, Bureau of Reclamation, Columbia Cascades Area Office, 1917 Marsh Road, (CCA-1607), Yakima, WA 98901-2058 or emailed to kmcgowan@usbr.gov.

# # #

The Bureau of Reclamation is a federal agency under the U.S. Department of the Interior and is the nation's largest wholesale water supplier and second largest producer of hydroelectric power. Our facilities also provide substantial flood control, recreation opportunities, and environmental benefits. Visit our website at https://www.usbr.gov and follow us on Twitter @USBR; Facebook @bureau.of.reclamation; LinkedIn @Bureau of Reclamation; Instagram @bureau_of_reclamation; and YouTube @reclamation.

Relevant Link:

www.usbr.gov/pn/programs/ea/wash/jkpgp/index.html